1 The project

An offshore piling project in Timor-Leste placed the order in late July 2026 with a 55-day delivery window. ASTM A252 Grade 2 was specified; after joint review the customer approved Q235B as the alternative.
Produced 508 and 813 mm heavy-wall spiral pipe, 5,000 m in total, with external FBE over the full length including beveled ends. Production ran about 45 days with no negative wall-thickness tolerance and 100% X-ray radiographic testing.
The customer sampled, measured and signed off before shipment; the pipe was dispatched on 19 October 2026 with felt, slings, end caps and shipping marks protecting the load.